Earned Value Formula:
From: | To: |
Earned Value (EV) is a project management technique that measures project performance and progress in an objective manner. It combines measurements of scope, schedule, and cost to provide a comprehensive view of project health.
The calculator uses the Earned Value formula:
Where:
Explanation: The formula calculates the value of work actually completed to date, providing an objective measure of project progress against the planned budget.
Details: Earned Value Analysis is crucial for project managers to objectively measure project performance, identify variances from the project plan, and forecast future performance based on current trends.
Tips: Enter the percentage of project completion (0-100%) and the total project budget (BAC). Both values must be valid positive numbers.
Q1: What's the difference between EV and actual cost?
A: Earned Value measures the value of work completed, while actual cost measures what was actually spent to complete that work.
Q2: How is % Complete determined?
A: % Complete can be measured through various methods including milestone completion, task completion, or physical measurement of work completed.
Q3: What is a good EV value?
A: Ideally, EV should equal the Planned Value (PV) for that time period, indicating the project is on track.
Q4: Can EV be greater than BAC?
A: No, EV cannot exceed BAC since it represents the value of work completed relative to the total budget.
Q5: What other metrics can be derived from EV?
A: EV is used to calculate Cost Variance (CV = EV - AC), Schedule Variance (SV = EV - PV), and performance indices (CPI, SPI).